RBS6601 Installation.pdf (1.39 MB)【資料名稱】:RBS6601 Installation
【資料作者】:ericsson
【資料日期】:20100607
【資料語(yǔ)言】:英文
【資料格式】:PDF
【資料目錄和簡(jiǎn)介】:
1 Introduction 1
1.1 Target Group 1
2 Prerequisites 3
2.1 Documents 3
2.2 Tools 4
2.3 Equipment 4
2.4 Conditions 5
3 Work Process for Installing the RBS 7
4 Connecting the ESD Wrist Strap 9
5 Unpacking and Checking the Materials 11
6 Installing the Main Unit 13
6.1 Adjusting the Movable Brackets 13
6.2 Earth Grounding the Main Unit 15
6.3 Installing the Main Unit in the Rack 16
6.4 Installing a Second Support System (WCDMA Only,
Optional) 17
6.5 Installing a Second Digital Unit in the Support System
(GSM Only) 19
7 Connecting the Power Supply 21
8 Connecting the External Alarm 23
8.1 Connecting the Built-in External Alarm 23
8.2 Connecting the SAU (Optional) 24
9 Connecting the GPS Solution (Optional) 27
10 Connecting the Site LAN (Optional) 29
11 Connecting the On-Site Transmission System 31
11.1 Connecting Transmission Interface E1/T1/J1 (WCDMA
Only) 31
11.2 Connecting Transmission Interface E1/T1 (GSM Only) 32
11.3 Connecting Transmission Interface Ethernet, Electrical
(WCDMA Only) 33
11.4 Connecting Transmission Interface Ethernet, Optical
(WCDMA Only,Optional) 34
12 Connecting the Optical Cables from the RRU 37
13 Verifying RBS Installation on Site 39
13.1 Inspecting RBS installation 39
13.2 Powering Up the RBS 41
13.3 Checking the RBS after Powering Up 41
14 Performing Concluding Routines 43
Reference List 45